FORM 6-K
SECURITIES AND EXCHANGE COMMISSION
WASHINGTON, D.C. 20549
Report of Foreign Private Issuer
Pursuant to Rule 13a-16 or 15d-16 of
the Securities Exchange Act of 1934
For the month of July, 2007
(Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.)
Form 20-F x Form 40-F o
(Indicate by check mark whether the registrant by furnishing the information contained in this form is also thereby furnishing the information to the Commission pursuant to Rule 12g3-2(b) under the Securities Exchange Act of 1934. )
Yes o No x
(If "Yes" is marked, indicate below the file number assigned to registrant in connection with Rule 12g3-2(b): 82-__________. )
N/A
Huaneng Power International, Inc.
West Wing, Building C, Tianyin Mansion
No. 2C Fuxingmennan Street
Xicheng District
Beijing, 100031 PRC
This Form 6-K consists of:
The announcement regarding the approval obtained on the project of
Zhejiang Huaneng Yuhuan Power Plant Phase II of Huaneng Power International, Inc. (the Registrant), made by the Registrant in English on July 25, 2007.
Document 1
(a Sino-foreign joint stock limited company incorporated in the Peoples Republic of China)
(Stock Code: 902)
OVERSEAS REGULATORY ANNOUNCEMENT
Approval Obtained on the Project of
Zhejiang Huaneng Yuhuan Power Plant Phase II
This announcement is issued pursuant to Rule 13.09(2) of the Rules Governing the Listing of Securities on The Stock Exchange of Hong Kong Limited (Listing Rules).
Huaneng Power International, Inc. (the Company) announced that the construction of the expansion project of 2 x 1000 MW domestic ultra-supercritical coal-fired generating units at Zhejiang Huaneng Yuhuan Power Plant Phase II has been approved by the National Development and Reform Commission recently.
The project will concurrently install flue-gas desulphurisation facilities, high-performance electrostatic precipitators and flue-gas continuous emission monitoring systems and adopt low-NOx combustion technique. Various emission indices at the power plant will satisfy the State´s environmental protection requirements. After the commencement of operation, the power plant will provide active contribution to meet the power demand for the economic development of Zhejiang Province.
The total investment amount of the project is estimated to be approximately RMB7.65 billion, of which 25% is equity capital to be funded by the Company, with the remaining to be funded by bank loans.
|
By Order of the Board |
As at the date of this announcement, the directors of the Company are:
Li Xiaopeng |
Qian Zhongwei |
Beijing, the PRC
25th July 2007
SIGNATURE
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the under-signed, thereunto duly authorized.
|
HUANENG POWER INTERNATIONAL, INC. |
|
By /s/ Huang Jian |
|
Name: |
Huang Jian |
|
Title: |
Company Secretary |
Date: |
July 26, 2007 |